Plumbing  ·  Level 4
Drainage System Installation I
Chapter 2: Install below ground drainage system
📚 8 Topics
What you will be able to do

By the end of this chapter, you will be able to:

  • Apply safety measures correctly to keep your work environment safe.
  • Prepare below ground drainage materials accurately using the working drawings.
  • Assemble the necessary drainage tools and equipment correctly for below ground tasks.
  • Prepare drainage trenches safely and accurately according to the job requirements.
  • Install drainage pipework following the system layout to the required standard.
  • Construct drainage access points correctly by following the proper work procedures.
  • Perform functionality tests safely and accurately to ensure the system works well.
  • Conduct housekeeping properly to maintain a clean and safe worksite.

Mastering these skills will help you build reliable drainage systems that keep communities safe and healthy.

Installing below ground drainage systems involves working in confined spaces, handling heavy materials, and exposure to various physical and environmental hazards. Safety on site is paramount to protect plumbing professionals from injury and to maintain operational efficiency. In Kenya, adherence to personal protective equipment (PPE) standards and workshop safety protocols ensures compliance with occupational safety laws while reducing accidents during drainage installation projects in schools, hospitals, and county government offices.

2.1 Personal protective equipment below

Personal protective equipment (PPE) is essential for plumbing professionals installing below ground drainage systems to prevent injuries from falling objects, sharp tools, chemical exposure, and dust inhalation. The correct use of PPE protects workers in environments such as construction of drainage lines in Nairobi schools or hospitals where site conditions can be hazardous. Understanding each PPE item’s role, proper use, and maintenance supports a culture of safety and compliance with Kenyan workplace safety regulations.

2.1.1 Hardhat/ Helmet

The hardhat or helmet is a fundamental PPE item for below ground drainage installation, designed to protect the head from impact, penetration, and electrical hazards. In Kenyan plumbing sites, such as county government drainage projects, falling debris from excavation or tools poses a significant risk, making helmets mandatory.

Protection against Impact and Penetration

  • Hardhats absorb and deflect the force of falling objects, preventing head injuries that could be fatal or cause long-term disability.
  • The helmet shell is constructed from rigid materials like high-density polyethylene (HDPE) to withstand sharp or heavy impacts common in trench excavation.

Electrical Hazard Resistance

  • Some helmets provide insulation against electrical shocks, which is critical when working near live electrical cables or buried utilities during drainage system installation.
  • Kenyan plumbing projects near electrical infrastructure require helmets certified for electrical resistance.

Proper Fit and Adjustment

  • Helmets must fit snugly on the head without causing discomfort to ensure continuous use.
  • Adjustable suspension systems inside the helmet allow customization for different head sizes and improve stability during movement.

Maintenance and Inspection

  • Regular inspection for cracks, dents, or degradation is necessary, especially after any impact incident.
  • Helmets should be cleaned with mild soap and water and stored away from direct sunlight to avoid material weakening.

2.1.2 Safety gloves

Safety gloves protect plumbing technicians’ hands from cuts, abrasions, chemical exposure, and infections when handling pipes, cement, and contaminated soil during below ground drainage installation.

Types of Safety Gloves for Plumbing

  • Leather gloves provide abrasion resistance and protection against sharp objects such as metal pipe edges or nails.
  • Chemical-resistant gloves made of nitrile or neoprene protect from exposure to solvents, adhesives, and sewage contaminants.

Importance of Proper Sizing and Dexterity

  • Gloves must fit well to allow dexterity for manipulating small tools and fittings without compromising protection.
  • Oversized gloves can reduce grip strength and increase the risk of accidents.

Prevention of Cross-Contamination

  • Using disposable gloves when handling sewage or contaminated materials minimizes infection risks.
  • Changing gloves regularly and proper handwashing after glove removal are critical hygiene practices.

Care and Maintenance

  • Gloves should be inspected for tears or holes before use.
  • Reusable gloves require cleaning according to manufacturer instructions and must be replaced when damaged.

2.1.3 Dustcoat / overall

Dustcoats or overalls shield the plumber’s skin and personal clothing from dirt, dust, chemical splashes, and moisture commonly encountered during excavation and pipe laying.

Material and Design Features

  • Overalls are typically made from durable, breathable fabrics such as cotton-polyester blends that resist tearing and allow air circulation.
  • High-visibility colors with reflective strips enhance worker visibility in low-light or busy construction sites.

Protection from Chemicals and Contaminants

  • Overalls prevent direct contact with hazardous substances like cement dust, sewage, and soil-borne pathogens.
  • In Kenyan hospitals or retail businesses installing drainage, overalls reduce the risk of spreading contaminants outside the worksite.

Comfort and Mobility

  • Properly fitted overalls should allow free movement essential for bending, lifting, and crouching in confined trenches.
  • Adjustable cuffs and elasticated waists improve comfort and prevent ingress of dirt.

Maintenance and Hygiene

  • Overalls must be regularly washed to remove contaminants and maintain a professional appearance.
  • Separate sets should be used for different tasks to avoid cross-contamination, especially when working near food or healthcare facilities.

2.1.4 Safety shoes / boots

Safety shoes or boots provide foot protection against heavy objects, sharp debris, slips, and electrical hazards during drainage system installation below ground.

Key Protective Features

  • Steel toe caps shield toes from crushing injuries caused by falling pipes or tools.
  • Puncture-resistant soles prevent injuries from stepping on nails, glass, or sharp stones common on construction sites.

Slip and Electrical Hazard Resistance

  • Outsoles with slip-resistant tread patterns improve stability on wet or muddy surfaces found in drainage trenches.
  • Electrical hazard-rated boots insulate the wearer when working near live electrical cables, a common hazard in urban plumbing projects.

Durability and Comfort

  • Boots made from waterproof leather or synthetic materials protect feet from water and sewage exposure.
  • Cushioned insoles and ankle support reduce fatigue during prolonged standing and walking on uneven ground.

Proper Fit and Care

  • Ill-fitting boots can cause blisters or reduce balance, increasing accident risk.
  • Regular cleaning and drying prevent material deterioration and fungal infections.

2.1.5 Safety goggles/ face mask

Safety goggles and face masks protect the eyes and respiratory system from dust, chemical splashes, and airborne pathogens encountered during excavation and pipe installation.

Protection against Dust and Debris

  • Goggles create a seal around the eyes, preventing soil particles and cement dust from causing irritation or injury.
  • Face masks filter airborne dust and spores, reducing respiratory problems common among workers exposed to fine particles.

Chemical Splash Protection

  • Goggles made from impact-resistant polycarbonate shield eyes from splashes of adhesives, solvents, or sewage.
  • In hospitals and food retail projects, masks reduce inhalation of harmful fumes and bioaerosols.

Types of Masks and Their Uses

  • Disposable dust masks offer basic protection against non-toxic dust.
  • Respirators with replaceable filters provide higher protection levels for chemical or biological hazards.

Proper Fit and Usage

  • Goggles and masks must fit snugly to ensure effective protection without fogging or air leaks.
  • Training on correct donning and doffing techniques prevents contamination and prolongs equipment life.

2.1.6 Workshop SOP's, rules and regulations

Standard Operating Procedures (SOPs), rules, and regulations form the backbone of safety management in plumbing workshops and on-site drainage installations. Compliance ensures legal adherence and reduces workplace accidents.

Purpose of SOPs in Plumbing Workshops

  • SOPs provide detailed instructions on safe work practices, equipment handling, and emergency response.
  • They standardize procedures across projects, ensuring every worker understands their safety responsibilities.

Kenyan Occupational Safety and Health Regulations

  • The Occupational Safety and Health Act (OSHA) 2007 mandates employers to provide a safe working environment and enforce PPE use.
  • Compliance with OSHA guidelines during below ground drainage installation prevents penalties and enhances worker welfare.

Common Workshop Rules

  • Prohibition of unauthorized personnel in hazardous areas to prevent accidents.
  • Mandatory use of PPE during all phases of drainage system installation.

Enforcement and Monitoring

  • Supervisors conduct regular safety audits and toolbox talks to reinforce compliance.
  • Incident reporting mechanisms encourage prompt action on hazards or breaches.

Training and Awareness

  • Continuous training on SOPs and safety regulations equips workers to identify risks and respond appropriately.
  • Use of visual aids, signage, and safety briefings improves understanding and adherence.

Practice Questions

  1. Explain five ways in which a hardhat protects plumbing professionals during below ground drainage installation. (10 marks)
  2. Discuss the importance of selecting the correct type and size of safety gloves for plumbing work. (10 marks)
  3. Describe the maintenance procedures necessary for dustcoats used in drainage system installation. (10 marks)
  4. Identify and explain five key features of safety boots that make them suitable for below ground plumbing work. (10 marks)
  5. Outline the role of workshop SOPs and OSHA regulations in ensuring safety during drainage system installation. (10 marks)
The rest of this chapter
🔒

Create a free account to open more of this chapter.

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒2.2 Types of below ground drainage materials / accessories

In Kenya’s plumbing industry, selecting appropriate below ground drainage materials and accessories is essential for ensuring durable, efficient, and safe wastewater management systems. Below ground drainage systems must resist soil pressure, corrosive agents,…

🔒2.3 Types of Drainage Tools and Equipment

In the installation of below ground drainage systems, the selection and use of appropriate tools and equipment is critical to achieving a durable and effective plumbing solution. Kenyan plumbing professionals must be familiar with a variety of hand and power t…

🔒2.4 Preparation of Drainage Trenches

In plumbing projects across Kenya, proper preparation of drainage trenches is foundational to ensuring efficient wastewater management and system longevity. Whether installing drainage for a commercial building in Nairobi or a residential estate in Kisumu, the…

🔒2.5 Installation of drainage pipework

The installation of drainage pipework is a critical phase in below ground drainage system construction. Proper pipework installation ensures efficient flow of wastewater, prevents blockages, and minimizes risks of leakage or contamination. In the Kenyan contex…

🔒2.6 Construction of Drainage Access Points

Drainage access points are essential components of below ground drainage systems in plumbing. They allow for maintenance, inspection, and cleaning, ensuring the system functions effectively and prevents blockages or failures. In Kenya, where many urban and per…

🔒2.7 Drainage systems functionality tests

In Kenya's plumbing sector, ensuring that below ground drainage systems function correctly before handover is essential to prevent costly repairs and health hazards. Functionality tests verify that the system handles wastewater efficiently without leaks, block…

🔒2.8 Housekeeping

In below ground drainage system installation, maintaining a clean and organized work environment is essential for safety, efficiency, and quality of workmanship. Kenyan plumbing professionals often work in confined trench spaces or busy construction sites wher…

Chapter Summary

This chapter provided a comprehensive guide to installing below ground drainage systems, beginning with the essential personal protective equipment necessary for safety such as hardhats, gloves, dustcoats, safety boots, and goggles, along with adherence to workshop rules and regulations. It then explored the various types of drainage materials and accessories including waste pipes, fittings, bends, tees, couplings, adapters, and supports like hangers and clamps. The chapter detailed the tools and equipment used in drainage installation, covering items such as hacksaws, trowels, spirit levels, drilling machines, and plumbing snakes. Preparation of drainage trenches was explained through marking, excavation, trench bottom preparation, and setting out pipes. The installation process was outlined step-by-step, from setting pipes and installing supports to cutting, assembling fittings, fixing pipes, checking alignment and slope, sealing joints, and fitting drainage fixtures. Construction of drainage access points was covered, including cleanouts, inspection chambers, septic tanks, bio digesters, and vent pipes. Finally, the chapter discussed various functionality tests to ensure system performance and concluded with the importance of proper housekeeping for care, maintenance, and storage of drainage components.

Self-Assessment

🔒 PDFDownload this self-assessment, with answers

A. Written Assessment

  1. Which personal protective equipment is essential to protect your head from falling objects during below ground drainage installation? (2 marks)
  2. Describe two key functions of pipe hangers in below ground drainage systems. (4 marks)
🔒20 more in this section.

Chapter Examination Questions

🔒 PDFDownload these examination questions, with model answers

SECTION A (40 Marks) - Answer ALL Questions

  1. Explain the importance of wearing a hardhat when installing below ground drainage systems on a construction site in Nairobi. (4 marks)
  2. Describe how safety gloves protect plumbing professionals during drainage pipe installation. (4 marks)
🔒18 more in this section.

Chapter Practical Activities

Practical 1: Prepare Drainage Trenches for Below Ground Drainage System Installation

Plumbing · Level 4
Drainage System Installation I
PRACTICAL ASSESSMENT
TIME: 4 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Prepare a drainage trench 9000mm long, 600mm wide, and 600mm deep with a smooth and level trench bottom.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
Spade100mm PVC drainage pipe
Tape measureSand
Mason's square
Plumb bob
Spirit level
Builders line
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Spade1 Pc per Candidate
2Tape measure1 Pc per Candidate
3Mason's square1 Pc per Candidate
4Plumb bob1 Pc per Candidate
5Spirit level1 Pc per Candidate
6Builders line1 Roll per 5 Candidates
7Dustcoat1 Pc per Candidate
8Safety boots1 Pair per Candidate
9Gloves1 Pair per Candidate
10100mm PVC drainage pipe2 m per Candidate
11Sand2 kg per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: Prepare Drainage Trenches
Used personal protective equipment: safety boots, dustcoat, gloves
(Award 1 mark for each PPE worn correctly or zero)
3
Interpreted the working drawing correctly to identify trench location and dimensions
(Award 3 marks for correct interpretation or zero)
3
Identified and assembled correct tools and equipment for marking and excavation
(Award 0.5 mark for each correct tool identified, maximum 2 marks)
2
Marked out the drainage line on the ground accurately using builders line and tape measure
(Award 5 marks for correct length and width marked out or zero)
5
Excavated the trench to specified dimensions: 9000mm length, 600mm width, 600mm depth
(Award 10 marks for correct excavation to dimensions or zero)
10
Prepared the trench bottom by leveling and smoothing using spirit level and sand bedding
(Award 7 marks for smooth, level trench bottom or zero)
7
Used tools and equipment correctly and safely during the marking and excavation process
(Award 3 marks for correct and safe use or zero)
3
Cleaned and stored tools and equipment properly after completion
(Award 3 marks for proper cleaning and storage or zero)
3
Disposed of excavated soil and waste materials properly without causing environmental hazard
(Award 4 marks for proper disposal or zero)
4
Sub-Total40
PRODUCT CHECKLIST
Trench length is 9000mm ± 50mm
(Award 3 marks for correct length or zero)
3
Trench width is 600mm ± 25mm
(Award 3 marks for correct width or zero)
3
Trench depth is 600mm ± 25mm
(Award 3 marks for correct depth or zero)
3
Trench bottom is level and smooth, free of loose materials
(Award 4 marks for level and smooth trench bottom or zero)
4
Trench sides are vertical and stable without collapse
(Award 3 marks for vertical, stable sides or zero)
3
Trench alignment follows marked drainage line correctly
(Award 4 marks for correct alignment or zero)
4
Sub-Total20
GRAND TOTAL60
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)

Practical 2: Set Out and Install Below Ground Drainage Pipework 1200mm x 600mm Trench

Plumbing · Level 4
Drainage System Installation I
PRACTICAL ASSESSMENT
TIME: 5 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Set out and install below ground drainage pipework 3 meters long with 100mm PVC pipe.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
Tape Measure100mm PVC Drainage Pipe
Spirit Level100mm PVC Pipe Elbow (90°)
Builders Line100mm PVC Pipe Tee
Hacksaw100mm PVC Pipe Coupler
Marking ChalkPVC Pipe Solvent Cement
Sand for Bedding
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1100mm PVC Drainage Pipe3 m per Candidate
2100mm PVC Pipe Elbow (90°)2 Pcs per Candidate
3100mm PVC Pipe Tee1 Pc per Candidate
4100mm PVC Pipe Coupler2 Pcs per Candidate
5PVC Pipe Solvent Cement1 small bottle per 5 Candidates
6Sand for Bedding1 bag per 3 Candidates
7Marking Chalk1 Pc per Candidate
8Builders Line1 roll per 5 Candidates
9Tape Measure1 Pc per Candidate
10Spirit Level1 Pc per Candidate
11Hacksaw1 Pc per Candidate
12Hand Gloves1 Pair per Candidate
13Safety Boots1 Pair per Candidate
14Dust Coat1 Pc per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: SET OUT AND INSTALL DRAINAGE PIPEWORK
Used personal protective equipment: Safety boots, Hand gloves, Dust coat
(Award 1 mark for each PPE used, maximum 4 marks)
4
Interpreted and followed the working drawing/layout correctly
(Award 3 marks for correct interpretation or zero)
3
Identified and assembled correct tools and equipment for the task
(Award 1 mark for use of each tool: tape measure, spirit level, hacksaw, max 2 marks)
2
Identified appropriate drainage materials based on the drawing
(Award 1 mark for each correct material identified: 100mm PVC pipe, elbow, tee, coupler)
3
Measured and marked out the pipe route and lengths accurately
(Award 2 marks for correct length 3m, 2 marks for correct marking of fittings positions)
4
Cut pipes to correct lengths using hacksaw safely and accurately
(Award 2 marks for safety and 2 marks for accurate cutting)
4
Assembled pipe fittings using solvent cement correctly
(Award 4 marks for proper jointing with no gaps or misalignment)
4
Set pipes to correct slope and alignment using spirit level and builders line
(Award 5 marks for correct slope of 1:40 and alignment)
5
Fixed pipes securely in trench bedded on sand as per specifications
(Award 4 marks for proper bedding and fixing)
4
Tested pipework for flow and leaks using water test
(Award 3 marks for successful water flow with no leaks)
3
Disposed of waste and cleaned tools and site properly
(Award 2 marks for proper disposal and cleaning)
2
Stored tools and equipment according to manufacturer's instructions
(Award 2 marks for correct storage)
2
Maintained tools and equipment in good condition
(Award 2 marks for proper maintenance)
2
Completed the task 100% as per working drawing and specifications
(Award 2 marks for full completion, zero if incomplete)
2
Sub-Total44
PRODUCT CHECKLIST
Finished pipework length is 3000mm ±10mm
(Award 2 marks for correct length)
2
Pipe slope is 1:40 (25mm drop over 1.0m length) ±5mm
(Award 3 marks for correct slope)
3
Pipe joints are firm, flush, and leak-free
(Award 3 marks for good joints and no leaks)
3
Pipe alignment is straight and follows the set out line within ±5mm
(Award 2 marks for alignment)
2
Pipe bedding is uniform, with sand properly compacted
(Award 2 marks for proper bedding)
2
Overall workmanship meets professional standards
(Award 4 marks for neatness, no damage, correct assembly)
4
Sub-Total16
GRAND TOTAL60
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)
🔒

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒Install pipe hangers and supports for 100mm PVC drainage pipe systemPractical 3
🔒Assemble and Fit Below Ground Drainage Pipe FittingsPractical 4
🔒Install Below Ground Drainage Fixtures Including Traps and Vent PipesPractical 5
🔒Construct Below Ground Drainage Access Points Including Manholes, Septic Tank, and Catch BasinsPractical 6
🔒Install drainage grates and frames for below ground drainage openingsPractical 7
🔒Check and Adjust Alignment and Slope of Below Ground Drainage PipesPractical 8
🔒Seal Joints and Connections of Below Ground Drainage PipesPractical 9
🔒Perform Water Flow Test on Installed Below Ground Drainage SystemPractical 10
🔒Perform Pressure and Air Tests on Below Ground Drainage SystemPractical 11
🔒Perform Backflow and Sump Pump Tests on Below Ground Drainage SystemPractical 12
🔒Conduct Visual Inspection and Odor Check of Below Ground Drainage SystemPractical 13
🔒Use and Maintain Drainage Tools and Equipment During Below Ground Drainage InstallationPractical 14
🔒Apply workshop SOPs, rules, and regulations during below ground drainage system installationPractical 15
Flashcards 20 cards Study deck ▾
Question
1

↻ Tap card to reveal answer
🔒

18 more in this section.

Create a free account
Test Yourself 19 questions Start quiz ▾
0%
0 / 2
🔒

17 more in this section.

Create a free account
Am I competent?

At the start of this chapter we promised you would be able to:

  • Apply safety measures correctly to keep your work environment safe.
  • Prepare below ground drainage materials accurately using the working drawings.
  • Assemble the necessary drainage tools and equipment correctly for below ground tasks.
  • Prepare drainage trenches safely and accurately according to the job requirements.
  • Install drainage pipework following the system layout to the required standard.
  • Construct drainage access points correctly by following the proper work procedures.
  • Perform functionality tests safely and accurately to ensure the system works well.
  • Conduct housekeeping properly to maintain a clean and safe worksite.

Tick each one you can genuinely do.

So, are you there yet?

You're competent when you can confidently do 50% or more of what this chapter promised.

Sign in to record how you're doing.